  BUILDING/FACILITY          
07-072  City Hall HVAC & Upper Floor Renovations   $     400,000.00  $   483,584.52    $      (83,584.52)  Complete 
05-073  Police Building Addition   $     900,000.00  $      6,714.46    $     893,285.54  Osborne & Associates approved as architect, design in process 
07-086  Fire Station #2   $  1,200,000.00        Osborne & Associates approved as architect, design in process, existing site is feasible, waiting on cost estimate 
    Total - Building/Facility   $  2,500,000.00  $   490,298.98  $                -    $  2,009,701.02  
   PARKS AND RECREATION           
05-018  Greenway Trail - Phase I  (Bradford Creek)   $     563,378.00  $   209,107.71  $                -    $     354,270.29  ALDOT being asked for bid date 
07-071  Greenway Trail - Phase II  (Bradford Creek)   $     551,000.00  $     67,832.47  $                -    $     483,167.53  Environmental Engineering Complete. Preliminary design in progress; 30% submittal received, property appraisals in progress 
05-041  Soccer Fields - Dublin Park   $     100,000.00  $   110,815.42    $      (10,815.42)  Complete 
   Total - Parks and Recreation   $  1,214,378.00  $   387,755.60  $                -    $     826,622.40  
   STREETS AND SIDEWALKS           
07-009  Intersection - Hughes Road/Old Madison Pike   $     250,000.00  $   272,985.92  $                -    $      (22,985.92)  Complete 
05-436  Intersection - Jay Drive & Wall Triana    $        5,000.00      $        5,000.00  Complete 
05-035  Intersection - County Line/I-565   $     105,000.00  $     53,650.00    $       51,350.00  Design by State Highway Department 
05-025  Intersection - Sullivan/Palmer    $  1,498,265.00  $1,363,945.33  $   117,835.23  $       16,484.44  Final punch list being worked this week 
05-051  Intersection - Wall Triana/Gillespie   $     336,892.00  $   310,749.05  $                -    $       26,142.95  Complete 
07-087  Intersection - Hughes Rd. and Hwy 72   $     218,000.00    $         800.00  $     217,200.00  Meeting held with ALDOT, public work session held, bid process to begin, final design in progress 
07-088  Intersection - Rainbow Dr. and Hwy 72   $       55,000.00    $         800.00  $       54,200.00  Meeting held with ALDOT, public work session held, bid process to begin, topo ordered, design in progress 
07-089  Intersection - Wall Triana and Brownsferry Rd.   $       75,000.00      $       75,000.00  Public work session held, bid process to begin, updated topo received, waiting on utility relocation and final drawings 
05-093  Traffic Signal - Hughes/Will Halsey Way   $       40,000.00  $     24,201.76  $                -    $       15,798.24  Complete 
06-063  Traffic Signal - Mill Rd/County Line   $     130,000.00  $   140,830.38    $      (10,830.38)  Complete 
07-017  Traffic Signal - Eastview / Slaughter   $     120,000.00  $     73,754.23  $      5,500.00  $       40,745.77  Complete 
07-019  Traffic Signal - County Line/Crownridge   $     130,000.00  $      6,025.87  $   139,415.00  $      (15,440.87)  Complete 
05-126  Traffic Signal - Zierdt at Mountainbrook   $       50,000.00  $     57,100.87  $      5,350.00  $      (12,450.87)  Complete 
07-020  Traffic Signal - County Line / Palmer Rd.   $     100,000.00  $      3,285.00  $      1,000.00  $       95,715.00  Bid awarded to Temple Electric 
05-365  Sidewalk-Hughes Rd (Mill to OMP)   $       49,300.00  $     56,264.00    $       (6,964.00)  Complete 
07-036  Sidewalk - Joe Phillips (County Line to Corrine)   $       78,000.00  $      3,223.00    $       74,777.00  Design in Progress  
05-042  Sidewalk - Eastview (Hughes to Metta)   $       70,000.00  $         502.40    $       69,497.60  Bid package being compiled 
07-040  Sidewalk-County Line (Heritage School to Dock Murphy)   $     100,000.00      $     100,000.00  Scheduled for 2008 Construction 
07-041  Sidewalk-Gillespie Road from Triana to Wellington   $       29,000.00      $       29,000.00  Scheduled for late 2008 Construction 
07-027  Bridge - Wall Triana at Mill Creek   $     270,000.00  $      9,712.50    $     260,287.50  Scheduled for late 2008 Construction 
07-024  Bridges - 2 on Gillespie Rd.   $     250,000.00  $      3,237.50    $     246,762.50  Preliminary design complete, bid package being compiled 
07-029  Bridge - Mill Rd. at Mill Creek   $     385,000.00        
06-076  Balch Road Widening   $     838,000.00  $   343,776.86    $     494,223.14  Public comments are being reviewed, 60% design in progress 
07-090  Balch Rd. Improvements   $     314,772.00  $         698.81    $     314,073.19  Paving is complete, shoulder work in progress, final striping will begin after 14 day curing process 
05-039  Gillespie Road Extension   $  1,659,656.00  $1,710,965.77  $                -    $      (51,309.77)  Construction in progress 
07-050  Wall Triana Widening (Construction - Mill to Brownsferry)   $     500,000.00      $     500,000.00  Scheduled for late 2008 Construction 
07-051  Wall Triana Widening (Engineering from Brownsferry to Gooch)   $     250,000.00  $      1,100.00  $    38,000.00  $     210,900.00  PO issued for Engineering Design from Gillespie to Gooch 
07-091  Wall Triana Improvements - Gooch to the N City Limits   $     410,000.00  $      4,238.39      Meeting held with ALDOT, public work session held, bid process to begin 
07-092  Wall Triana Improvements - Madison Blvd. to Cleghorn   $     294,000.00  $      7,575.00  $      3,625.00    Meeting held with ALDOT, public work session held, bid process to begin 
05-140  Yancy Road   $       30,800.00  $     28,365.32    $        2,434.68  Complete 
07-044  Zierdt Road - Five Lanes   $     500,000.00      $     500,000.00  Design in Progress, Huntsville is managing the project 
05-419  RR-Quiet Zone Improvement (Shelton Rd)   $     128,000.00  $   156,159.36  $      1,788.33  $      (29,947.69)  Complete 
07-046  Fire Station #1 Parking Apron   $       20,000.00  $     37,682.99  $                -    $      (17,682.99)  Complete 
05-123  Fire/Police Training Facility Entrance Road   $       27,000.00      $       27,000.00  Scheduled for 2008 Construction 
07-047  Eastview Extension to Wall Triana   $  1,200,000.00  $     25,581.48  $    18,600.00  $  1,155,818.52  Boundary and Topo Survey received, preliminary design complete, ROW is being appraised 
07-010  Balch Road Extension to Mill Road   $  1,200,000.00  $   223,373.50  $    95,115.25  $     881,511.25  Under Construction 
   Total - Streets and Sidewalks   $11,716,685.00  $4,918,985.29  $   427,828.81  $  6,369,870.90  
   DRAINAGE           
05-027  Homestead drainage   $       91,900.00  $     84,507.64  $                -    $        7,392.36  Complete 
05-028  Mill/Telluride/Whisperwood drainage   $     175,800.00  $      6,287.14  $                -    $     169,512.86  New Route being Negotiated along Mill Rd. 
05-150  Silver Creek drainage   $       23,800.00  $     18,035.62  $                -    $        5,764.38  Complete 
05-520  Madison Towne Center   $       70,000.00  $      4,406.58  $                -    $       65,593.42  Complete 
05-592  Putnam Industrial Park   $       40,000.00      $       40,000.00  Scheduled for late 2008 Construction, final design in progress 
07-093  Downtown Drainage Improvements - Pension Row and Sullivan St.   $     150,000.00    $      8,973.00  $     141,027.00  Topographical Survey received, preliminary design in progress 
07-094  Detention Pond Modifications for Two (2) Year Storms   $     100,000.00      $     100,000.00  
07-095  Brownsferry North Side Drainage - Park Meadow Dr. to Holly Springs   $     125,000.00      $     125,000.00  Topographical Survey received 
   Total - Drainage   $     776,500.00  $   113,236.98  $      8,973.00  $     654,290.02  
             
   CONTINGENCY   $  1,600,000.00      $  1,600,000.00  
             
  TOTAL  $17,807,563.00  $5,910,276.85  $   436,801.81  $11,460,484.34